Mount Auburn Street: A Complete Streets Project

Most Recent Updates

Last updated on November 14, 2025

Mount Auburn Street Project Update

Week of November 17 - November 21, 2025

Traffic Line Striping - Overnight Work

Traffic line striping is scheduled for Monday, November 17, 2025, beginning at 9:00 p.m. and lasting approximately four hours. The work will take place in the recently paved area of Mount Auburn Street between Lloyd Road and Boylston Street.

Traffic Impacts

A paint truck will lead the operation, followed by a vehicle equipped with an arrow board to direct traffic and signal drivers to change lanes as needed. A police detail will be on site to escort and assist crews throughout the work. No lane closures are anticipated during this operation.

Concrete Sidewalk Pouring

Crews will be pouring concrete for the sidewalk and driveway apron at 760 Mount Auburn Street, as well as the curb bump-out at the intersection of Mount Auburn Street and St Mary’s Street.

Sidewalk Impacts

The sidewalk in the effected areas will be closed. A bypass sidewalk will be opened up while this work is being completed.

Access to driveways and parking lots may be temporarily impacted during sidewalk concrete pouring. Please note that the concrete will require time to cure, and any properties affected during this period will be notified in advance.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage & Tree Trench Installation

Crews will perform drainage installation on Mount Auburn Street between Boylston Street and School Street.

Tree trench installation will occur between Upland Road and School Street next week on Mount Auburn Street. 

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Loaming

A landscaper contractor will be loaming tree pits and grass strips along the eastbound sidewalks on Mount Auburn Street between Arlington Street and Ralph Piteri Terrace.

Sidewalk Impacts

Sidewalks will remain accessible.


Getting Around Coolidge Square

During construction in the Coolidge Square area, Watertown’s Economic Development team developed the below graphic to help residents get around Coolidge Square, whether by car, bike, bus, or walking. Keep up-to-date with any road closures, bus stop impacts, or parking limitations in the work detailed above!


About the Project

The Mount Auburn Street project was initiated after a conceptual design was endorsed by the Town Council in November 2018. The Project Team submitted the 25% Design to the MassDOT in January 2020, and MassDOT held a 25% Design Public Hearing on November 4, 2021. Since then, the project team has submitted 100% Design plans for the corridor. 

The Mount Auburn Street Project will transform the corridor into a Complete Street, providing safe and accessible options for all modes. This project will also provide increased efficiency on the MBTA Bus Route 71, improve traffic operations and pedestrian and bicycle accommodations, improve accessibility in compliance with the Americans with Disabilities Act (ADA), and improved aesthetics.