Work Continues to Advance Mount Auburn Street

We would like to share some updates on behalf of National Grid and the City regarding other work taking place on Mount Auburn Street to advance the project.

Update from National Grid

National Grid continues to replace the gas main that runs down the center of Mount Auburn Street. This work is taking place in advance of future Mount Auburn Street road reconstruction.

National Grid has encountered some unexpected conditions and has provided an updated timeframe for completion of the work:

  •  Taylor Street to Walnut Street:  Estimated completion in mid-June 2023.

  • School Street to Arlington Street:  Estimated completion in October 2023.

  • Arlington Street to Cambridge line:  Estimated completion in October 2023.

Work between Walnut Street and School Street has not begun yet.  It is anticipated to begin in October, 2023 and last through January, 2024.

We understand that this work has been impactful and appreciate residents' and businesses’ patience as construction continues.  Please contact National Grid with questions regarding the work at 508-760-7533.

Upcoming Water and Sewer Upgrades

The City will begin a water and sewer upgrade project for the Mount Auburn Street corridor later this spring. The water and sewer mains on the street have been inspected and are generally in good condition. The project seeks to improve reliance and resiliency by replacing and/or installing new water valves at various locations that allow the City to turn on and off the water mains.  Limited repairs on the sewer mains will also be performed.