Mount Auburn Street: A Complete Streets Project
Most Recent Updates
Last updated on December 10, 2024
Drainage Installation Work and Catenary Pole Removal Continuing
Newport Construction is continuing drainage installation at the intersection of Arlington Street and Grove Street.
Catenary Pole Removal Continues
Work to remove the catenary poles is ongoing and will take place from 8 p.m. to 4 a.m. This phase of the project is expected to finish before the holiday season.
Traffic Impacts
Drainage Work: Lane shifts and temporary sidewalk closures may occur during this phase.
Catenary Pole Removal: Lane closures and lane shifts are expected, but no major disruptions to traffic are anticipated.
Parking Impacts
Street parking within the construction zones will be restricted during active work. Construction crews will clearly post signs in affected areas to notify drivers of parking closures.
(Note: All dates are approximate and will be dependent on weather conditions and any testing yet to be performed.)
About the Project
The Mount Auburn Street project was initiated after a conceptual design was endorsed by the Town Council in November 2018. The Project Team submitted the 25% Design to the MassDOT in January 2020, and MassDOT held a 25% Design Public Hearing on November 4, 2021. Since then, the project team has submitted 100% Design plans for the corridor.
The Mount Auburn Street Project will transform the corridor into a Complete Street, providing safe and accessible options for all modes. This project will also provide increased efficiency on the MBTA Bus Route 71, improve traffic operations and pedestrian and bicycle accommodations, improve accessibility in compliance with the Americans with Disabilities Act (ADA), and improved aesthetics.