Mount Auburn Street Project Update - Week of May 26 - May 29, 2026

No work will be performed on Monday, May 25, 2026, for Memorial Day.

Sidewalk Grading, Raising Structures, & Forming

Crews will be grading (measures used for proper drainage), raising structures (bringing structures to finished sidewalk elevation), and forming the eastbound sidewalk of Mount Auburn Street from School Lane to Belmont Street, and on Arlington Street and Grove Street. This work will begin on Tuesday, May 26, 2026 from 7:00am to 3:30pm. Learn about travel and parking impacts below.

Curb Removal and Reset

Curbs will be removed and reset on Arlington Street and Grove Street.

Traffic and Sidewalk Impacts

Sidewalks: During this work, pedestrians will be asked to use the sidewalks on the opposite side of the street. Once the work is completed, temporary walkways will be maintained to allow pedestrian access.

Traffic: During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage Installation

Crews will perform drainage installation on Mount Auburn Street between Richards Road and Stearns Road.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the drainage installation construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Tree Trenches

Crews will be installing tree trenches on Mount Auburn Street at Richards Road and Winthrop Street.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update - Week of May 18 - May 21, 2026

No work will be performed on Friday, May 22, 2026, in preparation for Memorial Day events.

Sidewalk Grading

Grading (measures used for proper drainage) of the eastbound sidewalk of Mount Auburn Street from School Lane to Belmont Street, and on Arlington Street and Grove Street. This work will start on Monday, May 18, 2026 from 7:00am to 3:30pm. Learn about travel and parking impacts below.

Sidewalk Forming

Once grading has been completed on the eastbound sidewalk of Mount Auburn Street from School Lane to Belmont Street, crews will be completing formwork to shape and contain the concrete for the sidewalks in this area

Curb Removal and Reset

Curbs will be removed and reset on Arlington Street and Grove Street.

Traffic and Sidewalk Impacts

Sidewalks: During this work, pedestrians will be asked to use the sidewalks on the opposite side of the street. Once the work is completed, temporary walkways will be maintained to allow pedestrian access.

Traffic: During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage Installation

Crews will perform drainage installation on Mount Auburn Street between Richards Road and Adams Avenue.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the drainage installation construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Conduit & Pedestrian Signal Installation

Crews will be installing conduits (underground electrical) and Pedestrian Signals at two locations on Mount Auburn Street.

  • Mount Auburn Street at School Street

  • 564 Mount Auburn Street

  • Mount Auburn Street at Arlington Street

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project - Update Week of May 11 - May 15, 2026

Sidewalk Removal

Excavation of the eastbound sidewalk on the corner of Mount Auburn Street and Arlington Street, and on Arlington Street and Grove Street. This work will start on Monday, May 11, 2026 from 7:00am to 3:30pm. Learn about travel and parking impacts below.

Curb Removal and Reset

Curbs will be removed and reset on the eastbound sidewalk of Mount Auburn Street between School Lane and Belmont Street.

Traffic and Sidewalk Impacts

Sidewalks: During this work, pedestrians will be asked to use the sidewalks on the opposite side of the street. The crosswalk at the intersection of Arlington Street and Mount Auburn Street will remain accessible for crossing. Once sections of the sidewalk are removed, temporary walkways will be maintained to allow pedestrian access.

Traffic: During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Sidewalk Removal

Curb Removal

Drainage Installation

Crews will perform drainage installation at the intersection of Mount Auburn Street and Oakley Road.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the drainage installation construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Conduit & Pedestrian Signal Installation

Crews will be installing conduits (underground electrical) and Pedestrian Signals at two locations on Mount Auburn Street.

  • Mount Auburn Street at Lloyd Road.

  • Mount Auburn Street at Kimball Road.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update - Week of May 4 - May 8, 2026

Traffic Line Striping - Overnight Work

*Update on scheduled date for striping.

Traffic line striping is scheduled for Thursday, May 7, 2026, beginning at 7:00 p.m. and lasting approximately four hours. The work will take place in the recently paved area of Mount Auburn Street between School Street and Langdon Avenue.

Raising Buried Structures

Crews will be raising buried utility structures, such as manholes and valve boxes, within the newly paved area along Mount Auburn Street between School Street and Langdon Avenue on Wednesday, May 6, 2026.

Traffic and Sidewalk Impacts

For striping: A paint truck will lead the operation, followed by a vehicle equipped with an arrow board to direct traffic and signal drivers to change lanes as needed. A police detail will be on site to escort and assist crews throughout the work. No lane closures are anticipated during this operation.

For raising buried structures: During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.

Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

For striping: No impacts.

For raising buried structures: Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Sidewalk Excavation

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Norseman Avenue and Belmont Street will begin on Monday, May 4, 2026 from 7:00am to 3:30pm.

Traffic and Sidewalk Impacts

The sidewalk will be closed for excavation . A bypass sidewalk on the eastbound side will be opened up while this work is being completed.

Traffic on Mount Auburn Street will be narrowed and you can expect lane shifts, however traffic will be maintained in both directions.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage Installation

Crews will perform drainage installation between Richard Road and Oakley Road on Mount Auburn Street.

Crews will perform drainage installation between Chauncy Street and Adams Avenue next week on Mount Auburn Street. 

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the drainage installation construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Conduit & Pedestrian Signal Installation

Crews will be installing conduits (underground electrical) and Pedestrian Signals at two locations on Mount Auburn Street.

  • Mount Auburn Street at Lloyd Road.

  • Mount Auburn Street at Kimball Road.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update- Week of April 27 - May 1, 2026

Milling and Paving

Milling (removal of the top layer of pavement) and paving will occur on Mount Auburn Street between Boylston Street and Chauncy Street and on School Street between Porter Street and Adams Avenue.

Detours will be in place for this work. Please see details below

Traffic and Sidewalk Impacts

Continuing 4/27/2026 through 5/1/2026, a detour will be in place on School Street for milling and paving operations. The detour will be in place from 9:00 AM – 4:00 PM.

  • School Street will be closed between Mount Auburn Street and Adams Avenue.

  • Travelers heading toward the Cambridge line on Mount Auburn Street will be detoured via Adams Avenue to access School Street.

  • Travelers heading toward Watertown Square on Mount Auburn Street will be detoured via Winsor Avenue instead of utilizing School Street. Access to the latter portion of School Street will still be available via Adams Avenue if needed.

  • Traffic traveling on School Street toward Mount Auburn Street will be redirected to Adams Avenue and then back to Mount Auburn Street.

One travel lane in each direction on Mount Auburn Street will be maintained.

Continuing 4/27/2026 through 5/1/2026, detours will be in place on Winsor Avenue and Langdon Avenue for milling and paving operations. The detour will be in place from 9:00 AM – 4:00 PM

  • Winsor Avenue will not have access to Mount Auburn Street

    • “Residents Only” signage will be posted at the intersection of Maplewood Street and Winsor Avenue

  • Langdon Avenue will not have access to Mount Auburn Street

    • “Residents Only” signage will be posted at the appropriate intersection

  • Those needing to access Mount Auburn Street are advised to use parallel side streets such as School Street or Hillside Road

One travel lane in each direction on Mount Auburn Street will be maintained.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage installation & Test Pits

Drainage installation and test pit excavation will occur on Mount Auburn Street at Amherst Road.

Conduit Installation

Crews will be installing conduits (underground electrical) in multiple locations on Mount Auburn Street.

  • Mount Auburn Street at Arlington Street.

  • Mount Auburn Street at Kimball Road.

  • Mount Auburn Street at the Fire Station.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage Work Location

Mount Auburn Street Project Update - Week of April 21 - April 24, 2026

No work will be performed on Monday, 4/20/2026, due to the holiday.

Milling and Paving

Milling (removal of the top layer of pavement) and paving will occur on Mount Auburn Street between Boylston Street and Chauncy Street and on School Street between Porter Street and Adams Avenue.

Detours will be in place for this work. Please see details below

Traffic and Sidewalk Impacts

Starting 4/21/2026 through 4/24/2026, a detour will be in place on School Street for milling and paving operations. The detour will be in place from 7:00 AM – 4:00 PM.

  • School Street will be closed between Mount Auburn Street and Adams Avenue.

  • Travelers heading toward the Cambridge line on Mount Auburn Street will be detoured via Adams Avenue to access School Street.

  • Travelers heading toward Watertown Square on Mount Auburn Street will be detoured via Winsor Avenue instead of utilizing School Street. Access to the latter portion of School Street will still be available via Adams Avenue if needed.

  • Traffic traveling on School Street toward Mount Auburn Street will be redirected to Adams Avenue and then back to Mount Auburn Street.

One travel lane in each direction on Mount Auburn Street will be maintained.

Beginning April 21, 2026 through April 24, 2026, detours will be in place on Winsor Avenue and Langdon Avenue for milling and paving operations. The detour will be in place from 7:00 AM – 4:00 PM

  • Winsor Avenue will not have access to Mount Auburn Street

    • “Residents Only” signage will be posted at the intersection of Maplewood Street and Winsor Avenue

  • Langdon Avenue will not have access to Mount Auburn Street

    • “Residents Only” signage will be posted at the appropriate intersection

  • Those needing to access Mount Auburn Street are advised to use parallel side streets such as School Street or Hillside Road

One travel lane in each direction on Mount Auburn Street will be maintained.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Drainage installation & Test Pits

Drainage installation and test pit excavation will occur on Mount Auburn Street at Amherst Road and at Richards Road.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mast Arm Foundation Installation

Electrical contractors will be installing mast arm foundations on Mount Auburn Street at Palfrey Street and Irving Street.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update - Week of April 13 - April 17, 2026

Drainage Installation & Test Pits

Crews will continue drainage installation and excavate test pits on School Street between Mount Auburn Street and Adams Avenue. This work will be performed between 9:15 AM and 2:00 PM.

Once drainage and tests pits have been completed in this area, crews will relocate to Mount Auburn Street between Richards Road and School Street.

Traffic and Sidewalk Impacts

Continuing April 13 and 14, 2026, a detour will be in place on School Street.

  • School Street will be closed between Mount Auburn Street and Adams Avenue.

  • Travelers heading toward the Cambridge line on Mount Auburn Street will be detoured via Adams Avenue to access School Street.

  • Travelers heading toward Watertown Square on Mount Auburn Street will be detoured via Winsor Avenue instead of utilizing School Street. Access to the latter portion of School Street will still be available via Adams Avenue if needed.

  • Traffic traveling on School Street toward Mount Auburn Street will be redirected to Adams Avenue and then back to Mount Auburn Street.

Once the drainage work on School Street is complete, the street closure will be lifted. At that point, temporary lane shifts and occasional lane closures may occur; however, one travel lane in each direction on Mount Auburn Street will be maintained.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Tree Trench Installation & Saw Cutting

Tree trench installation and saw cutting (root pruning) will occur between Richards Rd and School Street next week on Mount Auburn Street. 

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Conduit Foundation Installation

Crews will be installing conduits (underground electrical) at the intersection of Mount Auburn Street at School Street and Boylston Street.

Mast Arm Foundation Installation

Electrical contractors will be installing mast arm foundations at multiple locations on Mount Auburn Street.

  • Mount Auburn Street at Palfrey Street and Irving Street

  • Mount Auburn Street at Common Street

  • Mount Auburn Street at Walnut Street

  • Mount Auburn Street at School Street

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update - Week of April 6 - April 10, 2026

Drainage Installation & Test Pits

Crews will continue drainage installation and excavate test pits on School Street between Mount Auburn Street and Adams Avenue. This work will be performed between 9:15 AM and 2:00 PM.

Traffic and Sidewalk Impacts

Beginning April 6 through April 10, 2026, a detour will be in place on School Street.

  • School Street will be closed between Mount Auburn Street and Adams Avenue.

  • Travelers heading toward the Cambridge line on Mount Auburn Street will be detoured via Adams Avenue to access School Street.

  • Travelers heading toward Watertown Square on Mount Auburn Street will be detoured via Winsor Avenue instead of utilizing School Street. Access to the latter portion of School Street will still be available via Adams Avenue if needed.

  • Traffic traveling on School Street toward Mount Auburn Street will be redirected to Adams Avenue and then back to Mount Auburn Street.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Tree Trench Installation & Saw Cutting

Tree trench installation and saw cutting (root pruning) will occur between Richards Rd and School Street next week on Mount Auburn Street. 

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mast Arm Foundation Installation

Electrical contractors will be installing mast arm foundations at the intersection of Mount Auburn Street at School Street and Boylston Street. Mast arm foundations are the base of traffic signals.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Mount Auburn Street Project Update- Week of March 30 - April 3, 2026

Drainage Installation & Test Pits

Crews will continue drainage installation and excavate test pits on Mount Auburn Street between Chauncy Street and School Street

Traffic and Sidewalk Impacts

Beginning March 30, 2026, a detour will be in place on School Street. Access to School Street from Mount Auburn Street will remain open; however, traffic traveling down School Street toward Mount Auburn Street will be redirected onto Adams Avenue and then back to Mount Auburn Street.

At times, a temporary sidewalk detour may also be required. When this occurs, pedestrians will be directed to use the sidewalk on the opposite side of School Street from the work area.

Police details will be stationed at both the School Street and Adams Avenue intersection and the Mount Auburn Street and Adams Avenue intersection to assist with and direct traffic.

(See detour map below)

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Tree Trench Installation

Tree trench installation will occur between Langdon Avenue and Adams Avenue next week on Mount Auburn Street. 

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.

Connecting with Coolidge Square Businesses Ahead of Construction

As we prepare for the upcoming Mount Auburn Street Project, we were pleased to host an in-person meeting with Coolidge Square businesses on March 19, 2026. Invitations were extended to all local businesses, and we sincerely appreciate those who took the time to attend, ask questions, and share feedback.

What We Covered

During the meeting, we walked through several key topics to help businesses better understand what to expect:

  • Points of contact for questions and concerns

  • Project design details

  • Estimated construction timelines

  • The sidewalk and curb installation process

  • Proposed loading zones within Coolidge Square

Staying Connected During Construction

Clear and consistent communication will be essential throughout the project. Businesses and residents can stay informed or reach out with questions in several ways:

For immediate concerns (construction, detours, etc.):

  • Call 311 in Watertown or dial 617-458-8311 (texting is also available)

  • Email: team@mountauburnstreet.com

For weekly updates:

  • Sign up for email updates at mountauburnstreet.com/stay-in-touch

Business Coordination During Sidewalk Work

Newport Construction will take a hands-on approach to coordinating directly with businesses:

  • The Newport Construction team will be connecting a crew member with each individual business to coordinate sidewalk work being done in front of storefronts.

  • Sidewalk work directly in front of businesses will be scheduled separately from general concrete work.

  • To minimize disruption, storefront work will take place during early morning or nighttime hours whenever possible.

  • MassDOT will determine when sidewalks are safe and accessible, and Newport will share those updates with businesses.

Project Design Highlights

At the meeting, the project designer presented renderings of the future Coolidge Square streetscape. These designs highlight:

  • A new placemaking area on Bigelow Avenue

  • A redesigned streetscape throughout Coolidge Square

  • Dedicated street parking

  • New bike lanes and improved roadway layout

Estimated Construction Timeline

Newport Construction also shared a preliminary schedule for sidewalk removal and installation. Please note that all dates are subject to change:

  • South Side of Mount Auburn Street (School Lane to Belmont Street):
    March 30 – April 24, 2026

  • Arlington Street and Grove Street:
    April 27 – May 8, 2026

  • South Side of Mount Auburn Street (Arlington Street to School Street):
    May 11 – July 10, 2026

  • North Side of Mount Auburn Street (School Street to Arlington Street):
    July 13 – September 4, 2026

  • Mount Auburn Street (School Street to Chauncy Street):
    September 8 – October 31, 2026

What to Expect: Sidewalk Replacement Process

To provide more clarity, Newport Construction outlined the steps involved in sidewalk reconstruction:

  1. Removal of the existing sidewalk

  2. Rough grading and preparation of the base

  3. Removal of existing granite curbing and installation of new curbs

  4. Formwork to shape and contain the concrete

  5. Concrete pouring and finishing

Proposed Loading Zones

We also discussed questions related to loading and deliveries. Four proposed loading zones are planned within Coolidge Square at the following intersections along Mount Auburn Street:

  • Dexter Avenue

  • Melendy Avenue

  • Elton Avenue

  • Kimball Road

See the loading zones in the Coolidge Square area!