Drainage Installation
Crews will perform drainage installation on Mount Auburn Street between Langdon Avenue and Winthrop Street.
Traffic and Sidewalk Impacts
During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.
Parking Impacts
Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.
Test Pits
Crews will be excavating test pits along Mount Auburn Street between School Street and Richards Road. This process is done to test the soil in this section of Mount Auburn Street.
Traffic and Sidewalk Impacts
During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.
Parking Impacts
Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm.