Mount Auburn Street Project Update - Week of September 2 through September 5, 2025

No work Monday, September 1, 2025 in observance of Labor Day.

Sidewalk Concrete Installation

Sidewalk concrete installation and pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Keenan Street from 7:00 AM to 3:30 PM. Concrete pouring is anticipated to begin between Belmont Street and Francis Street on Wednesday 9/3/2025. Notices have been provided to the properties directly affected within the pouring area. Details on travel and parking impacts are provided below.

Traffic and Sidewalk Impacts

The westbound sidewalk will be closed for this work starting again on Tuesday, September 2, 2025 at 7:00am. A bypass sidewalk on the westbound side will be opened up while this work is being completed.

Traffic on Mount Auburn Street will be narrowed and you can expect lane shifts, however traffic will be maintained in both directions. 

Parking Impacts

Parking on the westbound side of Mount Auburn Street between Belmont Street and Keenan Street will be prohibited while work is active between 7:00am and 3:30pm. "No parking" signs will be posted in the area and removed when work is completed each day. 

Drainage, Stormwater Tree Trench, and Hydrant Installation

Drainage, stormwater tree trenches, and hydrants will be installed along Mount Auburn Street between Arlington Street and Upland Road starting on Tuesday, September 2, 2025. Crews will work along this route throughout the week.

Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and the possibility of access to sideroad entrances being temporarily limited. One travel lane in each direction will be maintained on Mount Auburn Street. Detour signage will be posted should the access to sideroads be limited or closed during this work . Any sideroad access impacts is anticipated to be limited.

Some of this work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. The work in these areas will begin at 7:00 am each day and end before 5:00 pm.

Parking Impacts

Street parking in this construction area on Mount Auburn Street will be restricted. Please follow the parking closure signs that are posted by crews starting at 7:00 am each morning. Any parking closure signs that are posted will be removed from the area by 5:00 pm each day.

(Note: All dates are approximate and will be dependent on weather conditions and any testing yet to be performed.)