Concrete Placement
Concrete placement will take place on the westbound sidewalk along Mount Auburn Street between Melendy Avenue to Dexter Avenue.
Sidewalk Grading & Forming
Sidewalk fine grading will take place on Mount Auburn Street between Elton Avenue and Dexter Avenue.
Concrete Removal
Crews will be removing concrete sidewalks on Mount Auburn Street from Adams Street to School Street.
Curbing Removal & Reset
Crews will be removing curbs and resetting them on Mount Auburn Street from Adams Street to School Street.
Lowering Manhole Covers and Utility Structures
Crews will be lowering manhole covers and utility structures in preparation for the next section of road reconstruction on Mount Auburn Street between School Street and Amherst Road.
Sidewalk, Business access and traffic Impacts
Sidewalks: During this work, pedestrians will be asked to use the sidewalks on the opposite side of the street. Once the work is completed, temporary walkways will be maintained to allow pedestrian access.
Business Access: Pedestrians Needing access to businesses with in the active construction process will be directed to use rear entrances when available, or they will be escorted safely through the work zone by police details. Construction activities will be temporarily paused until pedestrians have safely entered the designated safe zone.
Traffic: During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street.
Parking Impacts
Street parking in the construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.
Drainage Installation
Two crews will perform drainage installation on Mount Auburn Street between Bates Road and Walnut Street.
Traffic and Sidewalk Impacts
During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will be maintained on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7:00 am each day and end before 5:00 pm.
Parking Impacts
Street parking in the drainage installation construction area on Mount Auburn Street will be restricted. Construction crews will post parking closure signs in those areas starting at 7:00 am and will be removing them from the area by 5:00 pm each day.